Project Description
Scope of work
Construction of new electrical system for Ras Tanura industrial area and demolish the old system. The work included; construction and installation of. 13.8KV high voltage underground power distribution system, 13.8KV high voltage pad mounted oil filled power distribution transformers, 13.8KV high voltage pad mounted power distribution SF6 multiway switch station (LBS), 2.4KV medium voltage power distribution switchgears at Substation No. 3, 2.4 KV Medium Voltage bus duct at Substation 1, Neutral Grounding Resistor (NGR), low voltage underground power distribution system, new street lighting system, testing and commissioning of the above equipment and cables.