Project Description

Scope Of Work

Installation of sampler probes, drive motors and turbine flow meters on the thirty crude loading arms, two automatic sampler skids on Sea Island # 1, 2, 3 and 4; prefabrication and installation of eight Nitrogen cylinder racks; installation of stainless steel sample purge lines for each loading arm; installation and testing of all electrical and instrumentation equipment; hydrotesting of piping, painting of piping, steel works, hot bolting & turn blinds.